Track3D Progress AI: User Guide
Overview
Track3D Progress AI is an assistant in Datagrid that answers questions about your construction projects in plain English. It combines three sources:
Source | What it provides |
Track3D | Actual progress from your site captures: projects, structures and levels, categories, stages, takeoff quantities, captures, designs, and stalled or slowed-down work |
Procore – Track3D Schedules | Planned start and end dates for each stage |
Procore – Track3D Manpower | Recorded crew sizes over time |
It uses only the sources your question needs. A simple progress question uses Track3D alone. A schedule or manpower question combines Track3D progress with your Procore documents.
What You Can Ask
Progress
"How far along is Oakridge Heights Phase II?"
"Show progress for Mechanical on the First Floor."
"What got done in the last two weeks?"
"Which stages are above 50%?"
Schedule Health
"Are we on track?"
"Which stages are delayed?"
"What's behind schedule but not yet overdue?"
"What is due this week?"
"How were we tracking at the end of July?"
Risk
"What needs attention?"
"Which stages have stalled?"
"Which stages are slowing down?"
Manpower and Forecasts
"Is the current crew enough to finish Drywall on time?"
"How many more workers do we need on Level 3 Electrical?"
"At current manpower, when will Rough-in finish?"
"What if we add 5 workers?"
"Drywall is already late. How many workers do we need to finish by 30 Nov, 2026?"
"Can we move workers from Level 2 to Level 5?"
Project Information
"Which projects do I have access to?"
"What structures and levels does this project have, and when were they last captured?"
"Which designs are uploaded for each level?"
"What categories, stages and takeoff quantities are set up?"
You can ask follow-up questions such as "only Mechanical" or "just Zone A". The assistant keeps the same project, area and dates from earlier in the conversation.
Setting Up Your Procore Documents
Schedule and manpower answers depend on two sets of files in Procore → Documents. Without them, the assistant can still answer progress questions, but it will tell you it can't work out schedule status or manpower.
Schedule File
Location: Track3D Schedules
File name: Match the Track3D project name, for example Oakridge Heights Phase II.csv.
Columns:
Column | Meaning |
| STRUCTURE for a structure-level row, ZONE for a zone-level row |
| Row identifier |
| Structure or level name |
| Zone name (zone rows only) |
| Work category, e.g. Fire Protection |
| Stage within the category, e.g. Rough-in |
| Planned start |
| Planned finish |
Manpower File
Location: Public Documents/Track3D Manpower
File name: Match the Track3D project name, for example Oakridge Heights Phase II.csv.
Columns: At minimum, a date and a worker count. Add structure, zone, category and stage columns if you want manpower matched to specific work. The more detail you record, the more precise the answers.
Naming Rules
Structure, zone, category and stage names must match the names in Track3D.
Capital letters and extra spaces don't matter, but different wording does: "Level 1" and "First Floor" won't match.
Keep one schedule file and one manpower file per project.
If the assistant finds more than one possible file, it will ask you which one to use.
How the Answers Are Worked Out
Progress
Progress % = completed quantity ÷ planned (takeoff) quantity × 100
If a stage has no planned quantity, its Progress % shows as —.
Schedule Status
Status | Meaning |
Not Started | Before the planned start, and no progress yet |
Started Early | Before the planned start, but work has begun |
On Track | Progress is at or ahead of where the schedule says it should be |
Behind Schedule | Still within the planned dates, but progress is below where it should be |
Delayed | The planned finish date has passed and the work isn't complete |
Completed | Completed quantity has reached the planned quantity |
— | Can't be determined, usually because the stage has no planned quantity |
"Where it should be" (Expected %) assumes work progresses evenly between the planned start and finish dates, counted in calendar days.
Variance = Actual % − Expected %.
For example, 35% actual against 55% expected is -20%.
Progress Alerts (from Track3D)
Alert | Meaning |
Stalled | No progress in the most recent period. Completed stages are never marked stalled. |
Slowed down | Less progress this period than the period before |
Stalled is not the same as Delayed. A stage can be delayed but still moving, or stalled but still within its planned dates.
Manpower
Productivity: Quantity completed per worker per day, measured on your own project. It compares progress and crew size over the same recent period, normally the last 7 days.
Required manpower: Remaining quantity ÷ (days left × productivity), rounded up to whole workers.
Forecast finish: When the work will finish at the current crew size and productivity.
Forecast Delay: The planned finish hasn't passed yet, but at the current pace the work will finish late.
High manpower increase: Flagged when the required crew is more than twice the current crew. Productivity doesn't always keep up when a crew grows that much (space, sequencing, materials and supervision all limit it).
All manpower figures are estimates based on recent performance.
Reading the Answers
Answers come as tables, followed by a short summary of what matters most (for example, how many stages are delayed, the largest shortfall against schedule, or where extra crew is needed).
What You'll See
Indicator | Meaning |
🟢 🟡 🔴 next to Progress % | 70% or more · 40–69% · below 40% |
— | The value isn't available or can't be worked out reliably. A short explanation usually follows. |
+12% / -18% in Variance | Ahead of (+) or behind (−) where the schedule says the work should be |
+3 in Additional Manpower | Workers needed on top of the current crew. 0 means the current crew is enough. |
25 ft²/person/day | Productivity: quantity completed per worker per day |
High manpower increase | The required crew is more than twice the current crew. Treat this figure as a rough starting estimate. |
Days Late | Calendar days since the planned finish date |
Dates are shown as 06 Jan, 2026.
Quantities of 100 or more are shown as whole numbers, and smaller quantities to at most 2 decimal places, with the unit (ft, ft², cy, count).
Crew sizes are always whole people, rounded up.
Sources
The assistant tells you which source each part of an answer came from. Schedule dates are labelled as coming from the Procore project schedule and crew sizes from Procore Track3D Manpower. Neither is ever presented as Track3D data.
Raw Files
It doesn't paste your raw schedule or manpower files into the answer unless you ask for them.
What the Assistant Won't Do
Make up data. It doesn't invent dates, quantities, crew sizes, productivity or recovery dates. If something is missing, it says so and shows what it does know.
Recommend a crew size without evidence. It only calculates productivity, and from that the crew needed, when progress and manpower records cover the same period. If they don't, it shows what it knows and leaves Required Manpower as —.
Spread crew numbers it can't place. If manpower is recorded only for a whole category or structure, it won't divide it evenly across stages.
Use another project's files. It only uses the schedule and manpower files for the project you're asking about.
Promise "on time" after a deadline has passed. For work that is already late, it reports it as Delayed. Give it a new target date and it will work out the crew needed to meet that date.
Change anything. It only reads data. It can't edit progress, schedules or manpower in Track3D or Procore.
Show data you can't access. It only sees the Track3D projects your account can see.
Troubleshooting
What You See | What to Check |
"No corresponding Procore schedule was found" | The schedule file is in |
"Manpower-based analysis cannot be completed" | The manpower file is in |
"X scheduled stages could not be matched" | Structure, category and stage names in your schedule file match Track3D exactly. |
Progress % or status shows — | The stage has a planned (takeoff) quantity in Track3D. |
"Productivity cannot be calculated" | The manpower file has dated records covering a period when progress was also recorded. |
The assistant asks which project you mean | Use the project's full name, or pick from the options it offers. |
A project is missing | Ask your Track3D project administrator to give you access. |
Getting Help
Email [email protected] and include:
The question you asked
The project name
Roughly when you asked it
A screenshot or link to the Datagrid conversation, if possible
Related Articles
Progress Dashboard Overview
Progress Without Takeoff Values