Track3D allows you to compare planned progress, actual progress, and required progress for each stage of work. You can also forecast completion timelines, analyse installation rates, and calculate manpower requirements — all within the platform.
Forecasting & Predictions
Forecasts help users understand when a stage is likely to be completed based on:
Planned rates
Recent rates
Required rates
Average rates
If multiple stages are selected or if key data is missing, forecasting will not be displayed.
Viewing Stage Details
Go to the Progress Trends page and select the hierarchy level and stage you want to analyze.
Click on the stage name to open detailed progress insights.
You will see the following information:
Planned Installation Rate: Expected work rate based on scheduled dates.
Recent Installation Rate: Average rate over the last 4 weeks.
Required Installation Rate: The rate needed to finish on time.
Average Installation Rate: Average rate since the start of the project.
Each rate card includes:
Work rate per week
Estimated completion date
Ahead/behind schedule status
If takeoff quantities or schedule dates are not available, certain details may not be displayed such as required Manpower, recent rate.
Calculating Required Manpower
Click on the stage name to access the manpower calculation tool.
Enter the manpower used during the last capture period. Track3D will calculate how many people are required to meet the scheduled end date.
If schedule dates or takeoff values are missing, the system will not allow manpower calculation.
Viewing Progress Trend Charts
Planned progress (if schedule data is available)
Actual progress up to the latest capture
Forecasted progress based on selected installation rate
Installation Rate Chart Shows:
Work completed per capture
Planned installation rate
Required installation rate (weekly)
Forecasted rates when applicable
Forecasting is visible only when the prediction toggle is enabled.
Limitations & Notes:
Forecasts require takeoff values and scheduled dates.
Charts automatically switch between percentage view and absolute view based on your settings.
Predictions are only available for a single stage at a time.
Planned rate is selected by default.
Predictions at Zone Level :
Users can now view prediction data directly for zone-stage selections.
Available prediction metrics include:
Planned Rate
Recent Rate
Required Rate
Average Rate
Estimated Completion Dates
Predictions are reflected on Line charts and Bar graphs
Users can also:
Enter manpower values
View required manpower calculations
Save zone combinations within Saved Views
Export reports containing zone information
If temporary schedules already exist and the user enables Predictions, those schedules are automatically applied to the prediction view.
Updated Terminology
Previous | Updated |
Schedule Dates | Changed Schedule |
Target Dates | Temporary Schedule |
Apply | Select |
Apply Schedule | Apply Temporary Schedule |
Change Schedule
When disabled: Enable Scheduled Trends or Predictions to change schedules.
When enabled: Apply a temporary schedule to see changes in trends & predictions.
Multiple Combination Support
For multiple level-stage or zone-stage selections:
Each combination maintains its own temporary schedule.
Previously applied temporary schedules are indicated when reopening the side panel.
Update All can permanently update all selected combinations simultaneously.
Schedule Logs
Log icon replaces the previous "View Log" text.
Date format updated to: Jun 04, 2026 — Jun 14, 2026
Empty history now displays: No history yet
Logs remain downloadable after schedule updates.
Permissions :
Applying temporary schedules requires no additional permissions.
However, permanently updating the Work Schedule is restricted to users who have Work Schedule permissions.
We hope this article has been helpful. If you have any questions please reach out to [email protected]

